|
VICTORY
FOR ENVIRONMENTAL GROUPS IN PEAR TREE BOTTOM CASE
In a
landmark case for Jamaica’s environmental movement, high court
judge Justice Bryan Sykes has ruled in favour of Northern Jamaica
Conservation Association (NJCA), Jamaica Environment Trust (JET)
and four individuals in the Judicial Review case concerning the
granting of an environmental permit for part of the planned
1,918-room Bahia Principe hotel in Runaway Bay.
On
Tuesday, May 16th Justice Sykes quashed the
environmental permit granted to Hoteles Jamaica Piñero Limited (HOJAPI)
for Phase One of the hotel and ordered that the National
Environment and Planning Agency (NEPA) reconsider the application
for the project.
He ruled
that NEPA and the Natural Resources Conservation Authority (NRCA)
had not complied with the legal requirements of the
decision-making process and had therefore acted unfairly in
granting the environmental permit.
However,
in response to a request from the NRCA lawyers, the judge agreed
to a 21-day stay on the revocation of the permit to allow the
Respondents to prepare an appeal if they so choose.
In
delivering his judgement, Justice Sykes found that NEPA had failed
to consider all of the relevant environmental information,
including a critical marine ecology report that was missing from
the Environmental Impact Assessment (EIA). He said that given the
undisputed high ecological value of the resources of Pear Tree
Bottom, the absence of the marine ecology report was of
“tremendous significance” to the decision-making process which the
court was being asked to examine.
The judge
agreed with the Applicants that the public consultation process
had been flawed and that NEPA and the NRCA had failed to respond
to the legitimate concerns and expectations of stakeholders. He
found that NRCA had acted unfairly, stating that “unfairness is an
abuse of power.”
“The
difficulty for me,” he said, “was that it was known to both NEPA
and NRCA that the EIA was incomplete. How can you consult without
giving the public full, complete and accurate information?”
Justice
Sykes pointed out another serious flaw in the consultation
process: the fact that NEPA and the NRCA had ignored the
recommendations of the Water Resources Authority (WRA), another
government agency with which they were required to consult, before
issuing the permit on July 26, 2005.
The WRA
had communicated to the NRCA that they found the proposed sewage
disposal method, deep well injection, completely unsatisfactory
and that the EIA failed to specify an acceptable method for sewage
treatment for the hotel. The WRA also recommended increasing the
set-back requirements for the hotel in light of the recent Asian
tsunami experience. The judge said he could find no reason why
the advice of the WRA had not been considered.
The judge
was extremely critical of the EIA, describing it as “really poor.”
He pointed out serious deficiencies in the empirical work which
NEPA itself had recognised, especially where environmental data
were required to be assessed over time, such as water quality. He
found that there had been insufficient field assessment of the
flora and fauna, reliance on old, outdated information and on
anonymous and unverifiable sources, and no evidence that the EIA
had actually assessed the coral reefs or the potential impact of
the development on them.
In the
opinion of the judge, the defective EIA had important implications
for the monitoring programme: “How can you monitor what you don’t
know is there?” he asked.
With
respect to the Respondents’ claim that a delay in filing the suit
might have affected the rights of third parties, namely the
developers, the judge found that there had been no undue delay in
the filing of the suit within 10 weeks of the issuance of the
permit, given the burdensome task of the Applicants to present a
clear case based on detailed evidence. He commented that the suit
was brought by two non-profit organisations, which were “not awash
with funds” and which needed to consult their Boards and seek
costly legal advice before proceeding.
Furthermore, the judge said that no evidence had been presented to
the court indicating prejudice to a third party or that quashing
the permit would be detrimental to good public administration.
“No-one
can say that adhering to the rule of law is bad public
administration,” he said
Under the
NRCA Act, the NRCA is mandated to “take
such steps as are necessary for the effective management of the
physical environment of Jamaica so as to ensure the conservation,
protection and proper use of its natural resources.”
Justice
Sykes commented that given the importance of protecting the
environment, decision-making in cases such as this should attract
a high degree of scrutiny and that he had no choice but to give
precedence to the rule of law.
The
judgement was delivered on Tuesday morning in a session lasting
almost three hours. Several members of the press were present
along with representatives of NJCA and JET.
Justice
Sykes explained that although the written judgement was not quite
complete he had brought forward the ruling in light of the urgency
of the case. He commended counsel on both sides for the high
quality of the research and documentation they had provided.
The
Applicants in this case were represented by C. Dennis Morrison,
QC, and Julianne Mais-Cox of DunnCox Ltd., and the Respondents
were represented by Patrick Foster and Symone Mayhew of the
Attorney General’s department.
Wendy Lee
Northern Jamaica Conservation Association
Runaway Bay, St. Ann
Phone: 973-4305
E-mail:
NJCA@cwjamaica.com
or
Diana McCaulay/Candis
Hamilton
Jamaica Environment Trust
11 Waterloo Road, Kingston 10
Phone : 960-3693
E-mail:
jamentrust@cwjamaica.com
Briefing Paper - Large scale hotel development at Pear Tree Bottom.
Report of Public Meeting for Pear Tree Bottom Development.
Visit our Newsroom/Media Archive for more Press Releases..
|